Holding the Line | The Spec Sheet — September 2026
Lake Conestee Dam Restoration Project Greenville SC
The Spec Sheet  /  September 2026

Holding The
Line

A 130-year-old dam. Three million cubic yards of contaminated sediment. 500,000 people downstream. Kiewit built the solution — and our formliners were part of what they poured.

Greenville, SC Reedy River Kiewit Roller-Compacted Concrete Dam Restoration Cast-In-Place
Scroll
$47.2M
Total project value —
completed under budget
100 yr
Design life of the new dam —
built to handle 100-year storms
500K+
People protected —
drinking water downstream
1 yr+
Ahead of schedule —
completed October 2025
Project 01  /  Greenville, SC
Lake Conestee Dam new roller-compacted concrete structure
Lake Conestee dam construction detail
Greenville County, SC — Reedy River
01
SCDES · Kiewit Infrastructure South · Kleinschmidt Group

Lake Conestee Dam Restoration

130 Years of Risk, One Solution

The Lake Conestee Dam sits on the Reedy River just seven miles south of downtown Greenville, SC — built in 1892 to power Conestee Mill, designed to last fifty years, and still standing 130 years later. Behind it: an estimated three million cubic yards of sediment laced with metals, pesticides, and PAHs from decades of textile industry runoff. As long as the dam held, the cap held. But the structure was deteriorating, and the margin for error was gone.

Rather than attempt to repair the failing original structure — which risked disturbing the contamination — engineers chose a different path entirely. Kiewit Infrastructure South Co. was brought in under a progressive design-build contract to construct a brand-new roller-compacted concrete dam fifty feet downstream of the original. The new structure would take control of the river, leaving the old stone dam submerged and sealed. It's a solution that addresses both the structural failure and the environmental risk at once.

33 Days, Around the Clock

Construction began in January 2025, with a groundbreaking ceremony on February 28. To keep the project on schedule, Kiewit built an onsite concrete batch plant adjacent to the old mill — a critical decision that allowed continuous production throughout placement. For 33 straight days, day crews set formwork and night crews placed concrete in uninterrupted lifts. Moreover, the team sequenced the RCC placement to gain elevation quickly, reducing their exposure to the flashy watershed and the storm events that had previously set the schedule back.

Spec Formliners supplied the form liners for the concrete work on this project. The result is a finished dam face that reflects the care put into every pour — concrete that performs structurally and reads architecturally, even on infrastructure this demanding.

Owner
SC Dept. of Environmental Services (SCDES)
Project Value
$47.2 Million (under budget)
Contractor
Kiewit Infrastructure South Co.
Engineer
Kleinschmidt Group
Location
Reedy River, Greenville County, SC
Construction Type
Roller-Compacted Concrete (RCC) — Cast-In-Place
Groundbreaking
February 28, 2025
Completed
October 2025 — 1+ year ahead of schedule
Project Highlights
  • New RCC dam built 50 feet in front of the 130-year-old original — no disturbance to contaminated sediment
  • Designed to last 100 years and contain 100-year storm events
  • Protects drinking water for 500,000+ people downstream
  • Contains 3 million cubic yards of contaminated sediment — metals, pesticides, PAHs
  • Onsite concrete batch plant built adjacent to old mill for continuous production
  • 33 straight days of day/night continuous concrete placement
  • Progressive design-build delivery — Kiewit engaged from the earliest design phase
  • Completed more than a year ahead of schedule and under $47.2M budget
  • Protects the 400-acre Conestee Nature Preserve — an Audubon Important Bird Area
Lake Conestee dam concrete formwork detail
Reedy River new dam structure Greenville SC
Lake Conestee Nature Preserve and dam site context
"

You can build 100 dams. But there are always a few jobs that stick with you. This one had that.

Anthony Galantini, Project Manager — Kiewit  /  Lake Conestee Dam Restoration